A former worker at the quarry that supplied ballast for the Madrid-Seville line alleges the material can crumble under train loads. The judge is awaiting expert findings before deciding whether to hear him.

The collision between a derailed Iryo train and a Renfe Alvia travelling in the opposite direction at Adamuz, Córdoba, killed 46 people and injured more than 120 on 18 January 2026. The crash occurred on the Madrid-Seville high-speed line. Investigators are examining infrastructure and rolling stock, with human factors also under review; the initial technical focus has included a possible rail or weld fracture near kilometre point 318.

A former employee of the quarry that supplied ballast for the Madrid-Seville high-speed line has asked the Montoro court to investigate the stone used at the accident site. He says he has more than 30 years’ experience producing aggregates and railway ballast, and alleges that the material did not meet Adif’s technical requirements. His account remains a claim, not a finding by the court or its experts.

The worker told the court he was dismissed after refusing to take part in producing and selling ballast he considered non-compliant. The dismissal is the subject of court proceedings. That circumstance has led Judge Cristina Pastor to treat his testimony cautiously because he may have an interest in the case. He approached the court voluntarily on 9 October; his request for anonymity was granted on Friday the 13th.

He alleges that the ballast wears excessively and breaks under train loads, generating fine particles and weakening the track bed. He says it came from his former quarry and failed to meet Especificación Técnica Adif ET 03.360.004.0 and UNE-EN 13450. He has asked for a temporary suspension of train traffic while the material is checked, and offered to help identify the stones and their installation locations.

The former worker says mineralogical and petrographic analysis, including thin-section examination and X-ray diffraction, could distinguish the quarry’s stone from older ballast. He has also offered delivery records and other documents. Guardia Civil officers collected several kilograms of ballast at the site for analysis. On 30 October 2026, Pastor ordered sealed ballast and concrete-sleeper samples to be analyzed by the Eduardo Torroja Institute for Construction Science, with counter-tests by CEDEX. The court has also received ADIF-Alta Velocidad’s track-monitoring reports, emergency-works file and ballast supply and transport records.

Pastor acknowledged receipt of the submission and said she would wait for the judicial tests and expert examinations before deciding whether the proposed testimony was relevant and necessary. The distinction between receiving a filing and agreeing to hear a witness also arose in a separate Madrid court case, where requested testimony remained undecided.

The wider technical inquiry is examining rail components recovered from the derailment site, identified in court reporting as kilometre point 318.681. The rail assembly reportedly joined a section manufactured by ArcelorMittal in 2023 to another installed in 1989. Maquisaba carried out the weld under ADIF’s applicable rules. Investigators are examining whether the failure involved the rail itself or the weld. AITAT is also considering whether the rail broke about 22 hours before the derailment and whether the track-circuit system failed to detect the break.

The technical investigation, transferred from the former Railway Accident Investigation Commission to AITAT, remains unresolved. Judge Pastor has authorized AITAT to measure wear on the recovered rail samples, provided the measurements do not alter the evidence. The investigation has not ruled out a wider track failure involving sleepers and ballast, or rails, clips and welds, as a factor in the Iryo derailment; the ballast allegation remains a separate line of inquiry rather than an established cause.