Data centres will have to source 80% of their electricity from renewable energy under the sustainability decree approved by Spain’s Council of Ministers on 20 November 2026. The requirement uses hourly matching, rather than annual renewable-energy accounting, and applies until renewables exceed 90% of Spain’s national electricity mix. The decree was jointly proposed by the Ministry for the Ecological Transition and the Demographic Challenge and the Ministry of Economy, Trade and Enterprise. The Ministry for Digital Transformation and Public Administration also proposed it. The decree is derived from Royal Decree-Law 7/2026.
The rules also apply an additionality principle: qualifying renewable generation generally must have entered the electricity system no more than 36 months before a data centre begins operating. Exceptions apply to certain photovoltaic and biomass projects, as well as repowering projects. The renewable-energy obligation is scheduled to become fully mandatory for all facilities from 1 January 2032. An optional transition pathway sets a 60% threshold initially, rising to 70% in 2029 and 80% in 2032. The decree covers environmental performance and water efficiency. It also addresses resilience and cybersecurity, along with digital sovereignty, including the handling and protection of data. Facilities can be disconnected when the electricity network is under strain.
The government also approved a plan for the electricity transmission network through 2030, spokesperson Elma Saiz said after the Cabinet meeting. The plan addresses 47.7 gigawatts of new electricity demand, including demand from industry and data centres. Hydrogen production is also among the sectors covered. It sets out €17.142 billion in network investment by 2030, 146% more than under the current planning framework. Energy minister Sara Aagesen called it the largest investment programme in the country’s history and said demand would determine investment priorities for the first time.
The two decisions address the infrastructure demands associated with new facilities. Aagesen said data centres had been granted 15 gigawatts of grid-access capacity: six gigawatts on the transmission network and nine on distribution. A further 20 gigawatts of applications were awaiting access, while three gigawatts had emerged in the preceding three months. These figures refer to grid-access capacity and applications, not completed facilities or electricity already consumed. The rules also include an optional transitional period. The government says it will give operators flexibility while they meet the requirements.
Energy minister Sara Aagesen said that without the decree consumers could face an additional €5 billion a year on their electricity bills. She attributed the projected impact to higher wholesale electricity prices and the cost of producing more electricity from gas, not to an increase already recorded in household bills. The figure is a projected impact, not a reported change in bills.
Industrial consumers could pay 25% more for the electricity they use under one of the scenarios Aagesen cited. She said the estimate varies across scenarios. The government aims to prevent the large energy demand of data centres from putting pressure on the system and prices.
Aagesen described Spain as attractive to investors and said new centres should meet the decree’s sustainability and digital-sovereignty standards. Parts of the data-centre and technology sector have criticised the requirements, warning that obligations covering renewable energy and water efficiency, along with cybersecurity requirements, could make planned projects unviable and jeopardise billions of euros in proposed investment. A separate Canary Islands road plan also sets an energy-use target, though it concerns assessed road infrastructure rather than data centres.
The 2030 electricity plan focuses on the transmission network. Aagesen called it the largest investment in the country’s history and said demand would determine investment priorities for the first time.