The decree requires data centres to source 80% of their electricity from renewable energy within five years. It applies to facilities with grid-access capacity of at least 10 MW, including sites under the same owner at one location whose combined capacity reaches that threshold. Operators must meet both an 80% total renewable-coverage requirement and an 80% hourly-matching requirement: renewable electricity generated in each hour must cover at least 80% of that hour’s consumption. The rules allow on-site generation or qualifying power-purchase agreements with new renewable plants, generally no more than 36 months old, under contracts lasting at least six years. They also allow Red Eléctrica to order installations disconnected when necessary to protect the electricity system.
Spain DC had prepared a challenge to the rules and planned to request an interim suspension from the Supreme Court. The account said the association expected major technology companies to bring their own appeals, but it does not confirm whether Spain DC filed its case or whether other organisations joined.
The association’s legal arguments were expected to focus on the Government’s use of a royal decree to regulate the sector comprehensively. Spain DC considered the measure a regulatory development rather than a law. Its lawyers also intended to challenge the urgent procedure, which the association said lacked justification, along with provisions allowing suspension of grid-access rights for between one and three years. The final framework ties grid access to compliance and provides for load reductions or disconnection. Violations may also lead to compensation obligations and suspension of access or connection rights for up to three years.
The rules changed during drafting. An earlier draft account described a six-month compliance period after a grid-access contract, while the final decree gives data centres five years to meet the renewable-power requirement. Facilities that accept disconnection without compensation may follow a transitional pathway, with renewable coverage of 60% through 2028, rising to 70% through 2031 before reaching 80% from 2032. The Council of Ministers approved the framework on 20 November 2026. Royal Decree 1032/2026 was published in Spain’s official gazette on 21 November and entered into force on 22 November.
Spain DC, which the account said represents 350 companies, argued that the requirements could make projects impossible to deliver. It warned that uncertainty over the decree could halt data-centre investment in Spain and put €66.9 billion in planned investment through 2030 at risk. The government presented the framework as a response to the electricity-system impact of data-centre growth. A government-linked estimate put the potential annual electricity-cost overrun at €5 billion. The decree also includes efficiency requirements, with reporting indicating Class A standards for power-usage effectiveness and water-usage effectiveness.
The association also sought support from technology firms, including Amazon. Google and Microsoft are members of Spain DC. Energy-sector groups Aelec and the Asociación Empresarial Eólica publicly opposed the rules; so did Appa Renovables, alongside digital business association Adigital, according to the account. The policy followed more than 600 objections from the sector and a report by Spain’s National Markets and Competition Commission. The data-centre sector association also accused the Government of “ideological retaliation,” as reported by Sur in English.