Eight BYD Flash Charging stations, each rated at 1,500 kW, are awaiting activation in Spain. The hardware is in place, but the paperwork is not. As the year ends, BYD still cannot say when the chargers will go live.
Only one pilot station is running, in Leganés, Madrid. There, a Denza Z9 GT charged from 10% to 97% in less than nine minutes, beating BYD’s own Paris demo. The other stations remain in limbo as permits and approvals get tangled. It is still unclear whether Leganés is one of the eight pilots or a separate case.
Information from ANFAC, as of Q2 2026, 23.9% of Spain’s public EV charging points, 17,821 out of 74,503, were installed but not yet operational because of regulatory delays.
This is more than a few chargers: BYD’s whole Spanish strategy is on the line. Denza announced the plan in June: 300 ultra-fast chargers in Spain and 50 in Portugal by the end of 2027. Any car with a CCS2 connector can use them, at a price below 0.50 euros per kWh. Denza’s first buyers get 18 months of free charging. But eight stations represent just 2.7% of the Spanish goal. To catch up, BYD would need to open about 24 new stations every month next year, a steep climb.
The real problem is the paperwork, not the technology. De Aza, a BYD executive, calls the process “quite complex.” The latest ANFAC Electromobility Barometer backs this up: by the second quarter of 2026, almost 18,000 public charging points in Spain had been installed but not switched on. That is nearly a quarter of the network. Each charger faces separate access and city approvals, followed by electrical sign-offs and a supply contract. Different authorities can stall any step.
BYD tried to make the process easier. Its stations draw only 100 kW from the grid, while large on-site batteries handle charging bursts of 1,500 kW. This setup should avoid the usual headaches, including special medium-voltage lines and lengthy talks with utilities. Even with this advantage, BYD cannot promise that all eight pilots will be live in three months. The problem reaches beyond technical snags.
A regional analysis of the Valencian Community found that more than 2,000 charging points remain inactive there, with equipment installed but awaiting licenses and grid connections. The regional pattern mirrors the national challenge.
For now, the impact is limited: only the Denza Z9 GT can use the chargers at full power. The car starts at 115,000 euros. Other BYD models, such as the Dolphin and Sealion 7, use the first-generation Blade battery. They cannot charge at top speed, but can still use the stations at their own limits. That will change in 2027, when BYD plans to launch cars with the new Blade 2 battery, which can handle ultra-fast charging. That is 18 months sooner than BYD first said.
There is a risk: if BYD starts selling Blade 2 cars in Spain while the network remains limited to a few dealership chargers, the promise of five-minute charging falls flat. The real test is delivering working stations on Spain’s highways. Dealership showrooms alone will not prove the network works for drivers, and prices must stay low after the free charging ends.
The rollout starts with chargers at BYD dealerships and deals with large operators and energy firms, before standalone stations reach busy locations. The eight pilots are just the start. They showcase the technology but do not meet drivers’ travel needs. The crunch comes in 2027, when BYD’s network must work for drivers on real trips.
BYD is not alone. As reported earlier, established carmakers also face delays and shifting schedules as they try to electrify Spain. But BYD’s plan depends on a charging revolution, and paperwork could kill the momentum.
BYD’s struggle reflects a deeper problem in Spain’s EV push: installing hardware is easy; getting permission to use it is harder. Unless Spain speeds up its rules, it could fall behind just as new electric cars hit the market. For now, the network remains inactive beyond the pilot, leaving drivers waiting.