Spain’s new data-centre decree links grid access to renewable power and efficiency requirements. Operators must cover 80% of total consumption with additional renewables and match 80% of hourly use with same-hour renewable electricity.

A data centre seeking a grid connection in Spain must now show how it will meet new renewable-energy and efficiency requirements. Royal Decree 1032/2026 was approved on 20 November and published in the Boletín Oficial del Estado on 21 November 2026, taking effect the following day. Listed as BOE-A-2026-24439 in issue 290, the decree sets requirements covering energy and the environment, along with resilience and digital sovereignty, for data centres connected to electricity transmission or distribution networks. It follows Royal Decree-Law 7/2026 of 20 March, which called for a subsequent decree setting conditions for data-centre grid access.

The rules generally cover centres with access power of at least 10 MW, including groups at the same location under the same ownership that reach that threshold together. The decree also sets conditions for centres hosting certain public-sector systems, regardless of their power. Its text says data-centre access permits exceed deployment forecasts and compete for limited grid capacity. In the explanatory material to Royal Decree-Law 7/2026, the government said the aggregate capacity covered by granted permits, if operated continuously, would equal about half of Spain’s national electricity demand in 2025. The government warned that demand without associated new renewable generation could be met in significant part by combined-cycle gas plants, raising costs and emissions. It could also increase electricity imports and dependence on imported gas.

Renewable supply faces two separate tests. Operators must cover 80% of total consumption through additional renewable generation, using self-consumption or qualifying contracts with producers in Spain. In every hour, renewable electricity generated in that same hour must back at least 80% of the energy used. Deviations trigger payments calculated at rates set out in the decree. The decree provides a system-wide qualification: when renewables exceed 90% of national electricity generation in the relevant year n-2, the additionality and hourly-correlation requirements are treated as satisfied for an access application in year n. Once the threshold has been exceeded in a calendar year, it is treated as met for the following five calendar years.

The rules also set operational deadlines. Centres must reach the top energy-efficiency category under the prescribed methodology within two years of starting operation, and class A for water efficiency within one year. Until the European labelling system applies, the limits are a PUE of 1.25 and a WUE of 0.1. Annual verification begins after the relevant deadline. The decree’s sustainability requirements cover energy and water-use efficiency, plus renewable-energy additionality and the correlation between renewable generation and consumption.

For some facilities, a five-year transitional option allows participation in the automatic power-reduction system in exchange for gradually rising hourly renewable requirements. Centres using the option must pass system tests and be able to reduce consumption to zero when instructed by the system operator. Only facilities entering service before 31 December 2030 can use this route.

The decree also governs data location for centres hosting information systems classified as category ALTA under the Esquema Nacional de Seguridad. Content data and service-derived data must remain in the EU or EEA, along with their backups and replicas. Remote work from a third country is allowed only when technically essential, limited to what is necessary and logged. The records must be kept for at least five years.

Operators with IT power of at least 500 kW must submit specified energy and sustainability information to the Ministry for the Ecological Transition and the Demographic Challenge before 15 May each year. The ministry will publish the information, while protecting trade secrets and confidential business material. The decree’s approval was covered in earlier reporting.

Projects with permits but no grid connection have six months from the decree’s entry into force to demonstrate compliance with most requirements. A separate 12-month period applies to adapting to the sovereignty rules for centres hosting category ALTA systems. The decree provides for enforcement under applicable legislation covering electricity and energy efficiency, as well as digital sovereignty.

Richard Reid RUSSPAIN.com